The Contract Management (CMS)
module generates all the contract information from bid request through
tendering, progress payment to contract final closing.
Information available includes:
• Bills of Quantity for tender, the initial tender documents can
be prepared by direct input or by transferring data from the estimating
module (EST)
• Comparative analysis of unit rates on returned bids
• Log of questions and answers from/to bidders during the bidding
period
• Bid analysis of unit rates for use in contract or claims negotiations
• Contract bill of quantity sheet
• Progress Payment Certificates ready to sign, summary and detail
• Change order and contractor claim control
• Contract variation based on quantities for unit cost and cost
plus contracts or document change for lump sum contracts
• Control of submittals
• Control of bank guarantees
As the contract progresses and more detail design becomes available,
each item can be re-estimated for calculating the future addenda and contract
final value.
Data from this module is automatically transferred to the Capital Cost
Module (CCS) allowing accurate update of Actual Cost, Committed Cost and
Estimated Cost at Completion without any manual data re-entry.
The CMS keeps a record of payment history, allowing easy retrieval of
past Progress Payment Certificates.
Actual progress can be entered manually based on quantity installed to
date or as a percentage. Actual progress is entered on an accumulated
basis and progress for the period is calculated as (Accumulated progress
to date less Previous period accumulated progress). This concept avoids
carrying over to the next period “over stated” progress from
the previous period.
The progress measurement criteria defined in the Estimating module (EST)
is available within the CMS module. This concept provides an on-line procedure
for estimating the percent complete of each contract item.
|
The CMS automatically produces
the Progress Payment Certificate for each contract with the retention
calculation. Retention at level of contract item can be released totally
or partially as required.
CMS can be used to manage timesheet based contract of services; in that
case timesheet data can be transferred from the Resource Management Module
(LXS).
CMS can also be used to manage engineering service work where progress
is calculated based on the status of the document; in that case progress
data calculated in the Engineering Management Module (EMS) can also be
transferred.
Contract information is entered in the contracted currency; data is then
converted into the reference currency using appropriate exchange rate
and summarized automatically in the Capital Cost module (CCS) providing
tracing from Progress Payment to Cost Report. |